Getting Paid on Construction Projects:
A Guide for Subcontractors, Suppliers and Workers

Introduction

The Seattle Housing Authority (SHA) recognizes that prompt payment is critical for both businesses and individuals. We are concerned that subcontractors and suppliers are paid quickly by the contractors that SHA hires to complete our construction projects. Likewise, we want to help ensure that workers employed on our construction projects receive the appropriate wages. Unfortunately, however, payment is sometimes delayed or withheld, causing financial hardships for those not paid. State law provides a number of avenues to help protect the rights of those working on public construction projects.

The information that follows is a summary of some of those rights and a description of the process to follow in securing payment from a contractor or subcontractor on a public construction project. In addition to a description of the basic provisions of the law, we have made available a copy of the relevant portions of State law for your own review as well as sample forms you may use in filing claims.

We hope that this information will be helpful to you in protecting your rights to payment on public construction projects. If you have any questions, please feel free to contact any of the individuals whose names are listed at the end of this document.

Liz Alzeer
Contracting Manager

NOTE: The information contained in this document is not legal advice from the Seattle Housing Authority, and those due money on a public construction project may conclude that contacting an attorney is necessary in order to protect your rights to payment. While the laws referred to in this document are current as of the date of publication, they are frequently amended by the State Legislature. Whenever necessary, you should refer to a current version of the law itself, or contact your legal advisor.

Preventing payment disputes

The following preventative steps may assist you in ensuring that you are paid for your work on a public construction project.

1. Know the contractor you’re working for. It is important that you carefully investigate the contractor you are considering becoming a subcontractor or supplier to prior to entering into a contract with them. Contracting with a contractor with a track record of non-payment or slow payment to subcontractors and suppliers may have a negative impact on your firm’s finances.

· Ask the contractor for references of other subcontractors and suppliers they have worked with. Call the references to find out about the contractor’s payment practices.

· Call the State Department of Labor and Industries at (360) 902-5226, or visit their Web site at https://wws2.wa.gov/lni/bbip/contractor.asp to find out if any claims have been filed against the Contractor’s Bond, required by State law for all licensed contractors.

· Call the local Better Business Bureau, or visit their Web site at http://www.thebbb.org/ to find out if there have been any complaints filed against the contractor.

2. Have a clear written agreement of what you will provide and what the contractor will pay. Many misunderstandings about payment can be avoided if you make sure you have a clear written agreement about what services or supplies you will provide and how much (and when) the contractor will pay you.

3. Provide the contractor with a clear, written invoice. A contractor may not pay you until they are satisfied that you have billed them properly for the work you performed or for the supplies and materials you provided. Make sure your invoice is clear and describes when you expect payment. This should be consistent with your written agreement with the contractor.

4. Attempt to discuss payment dispute issues with the contractor. If a payment dispute occurs and you are not paid promptly or not paid the correct amount, contact the contractor and identify why they have not paid you. A misunderstanding about further work they are expecting you to perform or a concern about the quality of your work may be the reason you are not receiving your payment. Try to resolve the outstanding issues in order to facilitate your payment.

5. Joint check from SHA to contractor and subcontractor or supplier. The Seattle Housing Authority does not ever make direct payment to a subcontractor or supplier, except by court order. However, if SHA receives a written request for issuance of a check made payable to both the contractor and a subcontractor or supplier, we will honor such a request. The request must be signed and notarized by an authorized representative of both the contractor and the subcontractor or supplier.

Your rights under the law

Many times, despite taking preventative measures, payment disputes occur and it becomes necessary to take additional legal steps to protect your rights to payment. There are two important resources that are available to subcontractors, suppliers, materialmen, and workers to help ensure they are paid for work on a public construction project.

Contract Bond: On every public construction project of $35,000 or more, the Seattle Housing Authority obtains from the contractor a Contract Bond (also known as a Performance and Payment Bond), normally in the amount of 100% of the amount of the contract. The Bond is a guarantee by the contractor’s bonding company (or surety) that they will ensure that the public construction project is successfully completed, and that all subcontractors, suppliers, materialmen, and workers will be paid for their work on the project. State law provides that you may file a claim of lien against this Bond in order to protect your rights to payment for work performed or supplies provided on a public construction project. On public construction projects less than $35,000, SHA assumes the liability for claims filed against the protections normally afforded by a Contract Bond, and filed consistent with the requirements of State law for claims against a Contract Bond.

Retainage: The Seattle Housing Authority withholds from the contractor 5% of each payment we make to the prime contractor on public construction projects of $35,000 or more. This 5% amount is known as Retainage and is held as a trust fund to help ensure that subcontractors, suppliers, materialmen, and workers are paid for their work on the project. State law provides that you may also file a claim of lien against the Retainage in order to protect your rights to payment for work performed or supplies provided on a public construction project. On public construction projects less than $35,000, SHA assumes the liability for claims filed against the protections normally afforded by Retainage, and filed consistent with the requirements of State law for claims against Retainage.

Filing a claim against the Contract Bond or Retainage does not guarantee that you will be paid, but it is an important first step to help ensure payment. There are a variety of requirements that relate to when a claim must be filed and what you must do to "perfect" the claim.

Filing and renewal of claim

You may file a claim against the Contract Bond and Retainage after you have performed the work and not been paid, subject to the following restrictions:

1. End of claim filing period:

· The period for filing a claim against the Contract Bond ends 30 days after SHA has declared the contract complete and formally accepted the project (RCW 39.08.030).

· The period for filing a claim against the Retainage ends 45 days after SHA has declared the contract complete and formally accepted the project (RCW 60.28.011).

· To find out the date on which SHA has declared a public construction project as complete, you may call (206) 615-3375.  

· Click here for a copy of Notice of Claim of Lien Form.

2. Renewal:

· Once you have filed a claim against the Retainage, in order to preserve your legal rights, you must renew the claim every four months, or commence a lawsuit to foreclose on the claim.

· If you miss the four month renewal deadline, your claim against the Retainage will lapse and cease to be considered a properly filed claim. You may not re-file the claim.

· A claim against the Retainage may not be filed or renewed after the 45th day following the contract being declared complete by SHA.

· A claim against the Contract Bond may not be filed after the 30th day following the contract being declared complete by SHA. Claims against the Contract Bond do not have renewal deadlines and requirements.

· Click here for a copy of Renewal of Claim of Lien Form.

3. Pre-Claim Notice for Delivery of Materials, Supplies, or Equipment: State law requires that anyone furnishing materials, supplies, or equipment on a public construction project must provide a notice to the contractor within specified time limits that they have commenced delivery of the materials. The notice must state the name of the subcontractor who requested the delivery and must further state that a claim against the bond and/or retainage may be filed by the provider of the materials. Without such a notice being filed, no foreclosure action against a claim will be considered valid by the courts. The specified time limits for filing such a notice are different for protection from the Contract Bond (within 10 days after the first delivery of such materials) and Retainage (within 60 days of beginning to furnish such materials). (RCW 39.08.065 and RCW 60.28.015).

Click here for a copy of Notice of Delivery of Materials, Supplies, or Equipment Form.

4. Where to file your claim: A claim (and any subsequent renewal) against the Contract Bond and Retainage on a Seattle Housing Authority public construction project should be sent to:

Liz Alzeer
Contracting Manager
Seattle Housing Authority
120 Sixth Avenue North
P.O. Box 19028
Seattle, WA 98109-1028

A copy of the claim should also be sent to the contractor and the contractor’s bonding company. If you need information on the contractor’s Contract Bond, you may call our office at (206) 615-3375. We can provide you with the name and address of the bonding company and the Contract Bond number.

Click here for a copy of Notice of Claim of Lien Form.

5. Release of Claim If the contractor subsequently pays you, you should then send a Release of Claim of Lien form to the same parties to whom the claim form was sent. Click here for a copy of Release of Claim of Lien Form. 

Foreclosure and payment

1. Foreclosure: In order to "perfect" your claim against the Retainage and preserve your legal rights, you must commence a lawsuit for foreclosure on the claim. A foreclosure action must be filed in court prior to the claim lapsing. A claim may lapse if you file your claim or renewal of your claim after the deadlines noted above or if you fail to renew your claim within four months of filing the claim.

If all attempts to obtain payment from the contractor have failed and it becomes necessary to "perfect" your claim and commence a lawsuit to foreclose on the claim, you may want to consider hiring an attorney to assist you in the legal proceedings.

 2. Payment based on a claim: The Seattle Housing Authority does not make payments to subcontractors or suppliers who have filed a claim against the Retainage without a court order directing SHA to make such a payment. SHA does not review or pass judgment on a claim to determine if the amount claimed should actually be paid. That role is reserved for the courts.

Payment of claims against the Retainage is based on the following priority order established by State law:

· Claims by workers for payment of prevailing wages (the process described in this document applies to these prevailing wage claims also)

· Claims by the State Department of Revenue for unpaid taxes (no court order required)

· Claims by subcontractors, suppliers, and materialmen (court order required)

· Claims for other taxes due (no court order required)

· Claims by SHA (no court order required)

If an inadequate amount of money remains in the Retainage to cover all claims due to be paid, the protections provided by the Contract Bond become applicable and the amounts due to subcontractors, suppliers, materialmen, and workers should be paid by the contractor’s bonding company.

FOR FURTHER INFORMATION contact the following individuals:

Don Tucker, Sr. Contract Administrator, (206) 615-3475

  • For the name and telephone number of the Contract Administrator who can provide the following information about a project:

· for date of completion of an SHA construction contract
· for information on claims and releases filed
· for name of bonding company and contract bond number

Liz Alzeer, Contracting Manager, (206) 615-3470

  • For additional questions or information

Our address and fax number

Seattle Housing Authority
Purchasing Division
120 Sixth Avenue North
P.O. Box 19028
Seattle, WA 98109-3410
Fax: (206) 615-3410

Seattle Housing Authority • 120 Sixth Avenue North • PO Box 19028 • Seattle, WA 98109-1028 • (206) 615-3300