RCW 60.28.011. Retained percentage --
Labor and material lien created -- Bond in lieu of
retained funds -- Termination before completion -- Chapter
deemed exclusive -- Release of ferry contract payments --
Projects of farmers home administration -- General
contractor/construction manager procedure -- Definitions.
(1) Public improvement contracts shall
provide, and public bodies shall reserve, a contract
retainage not to exceed five percent of the moneys earned
by the contractor as a trust fund for the protection and
payment of: (a) The claims of any person arising under the
contract; and (b) the state with respect to taxes imposed
pursuant to Title 82 RCW which may be due from such
contractor.
(2) Every person performing labor or
furnishing supplies toward the completion of a public
improvement contract shall have a lien upon moneys
reserved by a public body under the provisions of a public
improvement contract. However, the notice of the lien of
the claimant shall be given within forty-five days of
completion of the contract work, and in the manner
provided in RCW
39.08.030.
(3) The contractor at any time may
request the contract retainage be reduced to one hundred
percent of the value of the work remaining on the project.
(a) After completion of all contract
work other than landscaping, the contractor may request
that the public body release and pay in full the amounts
retained during the performance of the contract, and sixty
days thereafter the public body must release and pay in
full the amounts retained (other than continuing retention
of five percent of the moneys earned for landscaping)
subject to the provisions of chapters 39.12 and 60.28 RCW.
(b) Sixty days after completion of all
contract work the public body must release and pay in full
the amounts retained during the performance of the
contract subject to the provisions of chapters 39.12 and
60.28 RCW.
(4) The moneys reserved by a public
body under the provisions of a public improvement
contract, at the option of the contractor, shall be:
(a) Retained in a fund by the public
body;
(b) Deposited by the public body in an
interest bearing account in a bank, mutual savings bank,
or savings and loan association. Interest on moneys
reserved by a public body under the provision of a public
improvement contract shall be paid to the contractor;
(c) Placed in escrow with a bank or
trust company by the public body. When the moneys reserved
are placed in escrow, the public body shall issue a check
representing the sum of the moneys reserved payable to the
bank or trust company and the contractor jointly. This
check shall be converted into bonds and securities chosen
by the contractor and approved by the public body and the
bonds and securities shall be held in escrow. Interest on
the bonds and securities shall be paid to the contractor
as the interest accrues.
(5) The contractor or subcontractor may
withhold payment of not more than five percent from the
moneys earned by any subcontractor or sub-subcontractor or
supplier contracted with by the contractor to provide
labor, materials, or equipment to the public project.
Whenever the contractor or subcontractor reserves funds
earned by a subcontractor or sub-subcontractor or
supplier, the contractor or subcontractor shall pay
interest to the subcontractor or sub-subcontractor or
supplier at a rate equal to that received by the
contractor or subcontractor from reserved funds.
(6) A contractor may submit a bond for
all or any portion of the contract retainage in a form
acceptable to the public body and from a bonding company
meeting standards established by the public body. The
public body shall accept a bond meeting these requirements
unless the public body can demonstrate good cause for
refusing to accept it. This bond and any proceeds
therefrom are subject to all claims and liens and in the
same manner and priority as set forth for retained
percentages in this chapter. The public body shall release
the bonded portion of the retained funds to the contractor
within thirty days of accepting the bond from the
contractor. Whenever a public body accepts a bond in lieu
of retained funds from a contractor, the contractor shall
accept like bonds from any subcontractors or suppliers
from which the contractor has retained funds. The
contractor shall then release the funds retained from the
subcontractor or supplier to the subcontractor or supplier
within thirty days of accepting the bond from the
subcontractor or supplier.
(7) If the public body administering a
contract, after a substantial portion of the work has been
completed, finds that an unreasonable delay will occur in
the completion of the remaining portion of the contract
for any reason not the result of a breach thereof, it may,
if the contractor agrees, delete from the contract the
remaining work and accept as final the improvement at the
stage of completion then attained and make payment in
proportion to the amount of the work accomplished and in
this case any amounts retained and accumulated under this
section shall be held for a period of sixty days following
the completion. In the event that the work is terminated
before final completion as provided in this section, the
public body may thereafter enter into a new contract with
the same contractor to perform the remaining work or
improvement for an amount equal to or less than the cost
of the remaining work as was provided for in the original
contract without advertisement or bid. The provisions of
this chapter are exclusive and shall supersede all
provisions and regulations in conflict herewith.
(8) Whenever the department of
transportation has contracted for the construction of two
or more ferry vessels, sixty days after completion of all
contract work on each ferry vessel, the department must
release and pay in full the amounts retained in connection
with the construction of the vessel subject to the
provisions of RCW
60.28.020 and chapter
39.12 RCW. However, the
department of transportation may at its discretion
condition the release of funds retained in connection with
the completed ferry upon the contractor delivering a good
and sufficient bond with two or more sureties, or with a
surety company, in the amount of the retained funds to be
released to the contractor, conditioned that no taxes
shall be certified or claims filed for work on the ferry
after a period of sixty days following completion of the
ferry; and if taxes are certified or claims filed,
recovery may be had on the bond by the department of
revenue and the materialmen and laborers filing claims.
(9) Except as provided in subsection
(1) of this section, reservation by a public body for any
purpose from the moneys earned by a contractor by
fulfilling its responsibilities under public improvement
contracts is prohibited.
(10) Contracts on projects funded in
whole or in part by farmers home administration and
subject to farmers home administration regulations are not
subject to subsections (1) through (9) of this section.
(11) This subsection applies only to a
public body that has contracted for the construction of a
facility using the general contractor/construction manager
procedure, as defined under RCW
39.10.060. If the work performed
by a subcontractor on the project has been completed
within the first half of the time provided in the general
contractor/construction manager contract for completing
the work, the public body may accept the completion of the
subcontract. The public body must give public notice of
this acceptance. After a forty-five day period for giving
notice of liens, and compliance with the retainage release
procedures in RCW
60.28.021, the public body may
release that portion of the retained funds associated with
the subcontract. Claims against the retained funds after
the forty-five day period are not valid.
(12) Unless the context clearly
requires otherwise, the definitions in this subsection
apply throughout this section.
(a) "Contract retainage"
means an amount reserved by a public body from the moneys
earned by a person under a public improvement contract.
(b) "Person" means a person
or persons, mechanic, subcontractor, or materialperson who
performs labor or provides materials for a public
improvement contract, and any other person who supplies
the person with provisions or supplies for the carrying on
of a public improvement contract.
(c) "Public body" means the
state, or a county, city, town, district, board, or other
public body.
(d) "Public improvement
contract" means a contract for public improvements or
work, other than for professional services.
[2000 c 185 § 1; 1994 c 101 § 1; 1992
c 223 § 2.]
NOTES: Effective date -- 1992 c
223: See note following RCW
39.76.011.
Waiver of rights, construction --
Application -- 1992 c 223: See
RCW
39.04.900 and 39.04.901.
RCW 60.28.015. Recovery from retained
percentage -- Written notice to contractor of materials
furnished.
Every person, firm, or corporation
furnishing materials, supplies, or equipment to be used in
the construction, performance, carrying on, prosecution,
or doing of any work for the state, or any county, city,
town, district, municipality, or other public body, shall
give to the contractor of the work a notice in writing,
which notice shall cover the material, supplies, or
equipment furnished or leased during the sixty days
preceding the giving of such notice as well as all
subsequent materials, supplies, or equipment furnished or
leased, stating in substance and effect that such person,
firm, or corporation is and/or has furnished materials and
supplies, or equipment for use thereon, with the name of
the subcontractor ordering the same, and that a lien
against the retained percentage may be claimed for all
materials and supplies, or equipment furnished by such
person, firm, or corporation for use thereon, which notice
shall be given by (1) mailing the same by registered or
certified mail in an envelope addressed to the contractor,
or (2) by serving the same personally upon the contractor
or the contractor's representative and obtaining evidence
of such service in the form of a receipt or other
acknowledgement signed by the contractor or the
contractor's representative, and no suit or action shall
be maintained in any court against the retained percentage
to recover for such material, supplies, or equipment or
any part thereof unless the provisions of this section
have been complied with.
[1986 c 314 § 5.]
RCW 60.28.021. Excess over lien claims
paid to contractor.
After the expiration of the forty-five
day period for giving notice of lien provided in RCW
60.28.011(2), and after receipt
of the department of revenue's certificate, and the public
body is satisfied that the taxes certified as due or to
become due by the department of revenue are discharged,
and the claims of materialmen and laborers who have filed
their claims, together with a sum sufficient to defray the
cost of foreclosing the liens of such claims, and to pay
attorneys' fees, have been paid, the public body may
withhold from the remaining retained amounts for claims
the public body may have against the contractor and shall
pay the balance, if any, to the contractor the fund
retained by it or release to the contractor the securities
and bonds held in escrow.
If such taxes have not been discharged
or the claims, expenses, and fees have not been paid, the
public body shall either retain in its fund, or in an
interest bearing account, or retain in escrow, at the
option of the contractor, an amount equal to such unpaid
taxes and unpaid claims together with a sum sufficient to
defray the costs and attorney fees incurred in foreclosing
the lien of such claims, and shall pay, or release from
escrow, the remainder to the contractor.
[1992 c 223 § 3.]
NOTES: Effective date -- 1992 c
223: See note following RCW
39.76.011.
Waiver of rights, construction --
Application -- 1992 c 223: See
RCW
39.04.900 and 39.04.901.
RCW 60.28.030. Foreclosure of lien --
Limitation of action -- Release of funds.
Any person, firm, or corporation filing
a claim against the reserve fund shall have four months
from the time of the filing thereof in which to bring an
action to foreclose the lien. The lien shall be enforced
by action in the superior court of the county where filed,
and shall be governed by the laws regulating the
proceedings in civil actions touching the mode and manner
of trial and the proceedings and laws to secure property
so as to hold it for the satisfaction of any lien against
it: PROVIDED, That the public body shall not be required
to make any detailed answer to any complaint or other
pleading but need only certify to the court the name of
the contractor; the work contracted to be done; the date
of the contract; the date of completion and final
acceptance of the work; the amount retained; the amount of
taxes certified due or to become due to the state; and all
claims filed with it showing respectively the dates of
filing, the names of claimants, and amounts claimed. Such
certification shall operate to arrest payment of so much
of the funds retained as is required to discharge the
taxes certified due or to become due and the claims filed
in accordance with this chapter. In any action brought to
enforce the lien, the claimant, if he prevails, is
entitled to recover, in addition to all other costs,
attorney fees in such sum as the court finds reasonable.
If a claimant fails to bring action to foreclose his lien
within the four months period, the reserve fund shall be
discharged from the lien of his claim and the funds shall
be paid to the contractor. The four months limitation
shall not, however, be construed as a limitation upon the
right to sue the contractor or his surety where no right
of foreclosure is sought against the fund.
[1979 ex.s. c 38 § 1; 1955 c 236 § 3;
1927 c 241 § 1; 1921 c 166 § 3; RRS § 10322.]
RCW 60.28.040. Tax liens -- Priority of
liens.
The amount of all taxes, increases and
penalties due or to become due under Title 82 RCW, from a
contractor or the contractor's successors or assignees
with respect to a public improvement contract wherein the
contract price is twenty thousand dollars or more shall be
a lien prior to all other liens upon the amount of the
retained percentage withheld by the disbursing officer
under such contract, except that the employees of a
contractor or the contractor's successors or assignees who
have not been paid the prevailing wage under such a public
improvement contract shall have a first priority lien
against the bond or retainage prior to all other liens.
The amount of all other taxes, increases and penalties due
and owing from the contractor shall be a lien upon the
balance of such retained percentage remaining in the
possession of the disbursing officer after all other
statutory lien claims have been paid.
[1985 c 80 § 1; 1971 ex.s. c 299 § 1;
1955 c 236 § 4. Prior: 1949 c 228 § 27, part; Rem. Supp.
1949 § 8370-204a, part; RCW 82.32.250, part.]
NOTES: Severability -- Effective
dates -- 1971 ex.s. c 299: See notes following RCW
82.04.050.
RCW 60.28.051. Duties of disbursing
officer upon completion of contract.
Upon completion of a contract, the
state, county or other municipal officer charged with the
duty of disbursing or authorizing disbursement or payment
of such contracts shall forthwith notify the department of
revenue of the completion of contracts over twenty
thousand dollars. Such officer shall not make any payment
from the retained percentage fund or release any retained
percentage escrow account to any person, until he has
received from the department of revenue a certificate that
all taxes, increases and penalties due from the
contractor, and all taxes due and to become due with
respect to such contract have been paid in full or that
they are, in the department's opinion, readily collectible
without recourse to the state's lien on the retained
percentage.
[1992 c 223 § 4.]
NOTES: Effective date -- 1992 c
223: See note following RCW
39.76.011.
Waiver of rights, construction --
Application -- 1992 c 223: See
RCW
39.04.900 and 39.04.901.
RCW 60.28.060. Duties of disbursing
officer upon final acceptance of contract -- Payments to
department of revenue.
If within thirty days after receipt of
notice by the department of revenue of the completion of
the contract, the amount of all taxes, increases and
penalties due from the contractor or any of his successors
or assignees or to become due with respect to such
contract have not been paid, the department of revenue may
certify to the disbursing officer the amount of all taxes,
increases and penalties due from the contractor, together
with the amount of all taxes due and to become due with
respect to the contract and may request payment thereof to
the department of revenue in accordance with the priority
provided by this chapter. The disbursing officer shall
within ten days after receipt of such certificate and
request pay to the department of revenue the amount of all
taxes, increases and penalties certified to be due or to
become due with respect to the particular contract, and,
after payment of all claims which by statute are a lien
upon the retained percentage withheld by the disbursing
officer, shall pay to the department of revenue the
balance, if any, or so much thereof as shall be necessary
to satisfy the claim of the department of revenue for the
balance of all taxes, increases or penalties shown to be
due by the certificate of the department of revenue. If
the contractor owes no taxes imposed pursuant to Title 82
RCW, the department of revenue shall so certify to the
disbursing officer.
[1967 ex.s. c 26 § 25; 1955 c 236 §
6. Prior: 1949 c 228 § 27, part; Rem. Supp. 1949 §
8370-204a, part; RCW
82.32.250, part.]
NOTES: Effective date -- 1967
ex.s. c 26: See note following RCW
82.01.050.
RCW 60.28.080. Delay due to litigation
-- Change order or force account directive -- Costs --
Arbitration -- Termination.
(1) If any delay in issuance of notice
to proceed or in construction following an award of any
public construction contract is primarily caused by acts
or omissions of persons or agencies other than the
contractor and a preliminary, special or permanent
restraining order of a court of competent jurisdiction is
issued pursuant to litigation and the appropriate public
contracting body does not elect to delete the completion
of the contract as provided by *RCW
60.28.010(3), the appropriate
contracting body will issue a change order or force
account directive to cover reasonable costs incurred by
the contractor as a result of such delay. These costs
shall include but not be limited to contractor's costs for
wages, labor costs other than wages, wage taxes,
materials, equipment rentals, insurance, bonds,
professional fees, and subcontracts, attributable to such
delay plus a reasonable sum for overhead and profit.
In the event of a dispute between the
contracting body and the contractor, arbitration
procedures may be commenced under the applicable terms of
the construction contract, or, if the contract contains no
such provision for arbitration, under the then obtaining
rules of the American Arbitration Association.
If the delay caused by litigation
exceeds six months, the contractor may then elect to
terminate the contract and to delete the completion of the
contract and receive payment in proportion to the amount
of the work completed plus the cost of the delay. Amounts
retained and accumulated under RCW
60.28.010 shall be held for a
period of thirty days following the election of the
contractor to terminate. Election not to terminate the
contract by the contractor shall not affect the
accumulation of costs incurred as a result of the delay
provided above.
(2) This section shall not apply to any
contract awarded pursuant to an invitation for bid issued
on or before July 16, 1973.
[1982 c 170 § 3; 1973 1st ex.s. c 62
§ 3.]
NOTES: *Reviser's note: RCW
60.28.010 was amended by 1982 c
170 § 1 changing subsection (3) to subsection (5).
Severability -- 1973 1st ex.s. c 62: See
note following RCW
39.04.120.
Change orders due to environmental
protection requirements, costs: RCW
39.04.120.
RCW 60.28.900. Severability -- 1955 c
236.
If any section, provision or part of
this chapter shall be adjudged to be invalid or
unconstitutional, such adjudication shall not affect the
validity of this chapter as a whole or any section,
provision or part hereof not adjudged invalid or
unconstitutional.
[1955 c 236 § 8.]