Rainier Vista Milestones

August 1999

Summer 2000

October 2000

2001

Grant Award  Counseling  planning City Council  approves  Memorandum of Agreement (MOA) with SHA
HOPE VI grant agreement awarded
Relocation planning and resident counseling begins
Residents and architects discuss housing design ideas
 

April 2001

May 2002

December 2002 August 2003
 Relocation Counseling  Relocation Phase I Citizen Review Committee created Groundbreaking Ceremony
One-on-one relocation counseling with residents completed
Relocation of Phase I completed  Groundbreaking ceremony marks official start of construction

Fall 2003

Winter 2004

November 2004 October 2005
Demolition  Construction Move In First Units
Demolition of Phase I completed
Housing construction in Phase I begins Residents move into first completed units
All rental housing in Phase I completed and occupied

September 2005

March 2006

February 2005

July 2005

McBride Genessee Gamelin  Neighborhood House Milestones
McBride Court and Park opens Housing Resources Group's Genesee Housing opens Providence Health System's Gamelin House opens Neighborhood House's Rainier Vista Center opens

February 2006

Spring 2006

Spring 2006

June 2006

home for sale Demolition began on the West side (phase II) of the site and was completed in June 2006 Park Building  Park Open
First home built by one of Rainier Vista's private builders sold Volunteers build Rainier Vista Park Rainier Vista
Park opens